Managing big projects: The lessons of experience
Infrastructure
has a problem. Even
for projects that are similar and that many companies have experience
building—think of roads, for example—delays and cost overruns are
common. Poor planning and execution, unbalanced contract terms and
conditions, inadequate controls, and lack of proper risk management
are rife.
According
to data from IHS Global Insight,
construction
productivity in many areas has worsened over the past decade; the IHS
Herold Global Projects Database
estimates
that large infrastructure, mining, and oil and gas projects, on
average, cost 80 percent more than budgeted and run 20 months late.
Major events like the Olympics and World Cup have to start on time,
but in recent decades, have always cost more than the original
projections.
Finally,
some projects meet these goals, but don’t work as intended.
Does
it have to be this way? Not necessarily. Some projects, after all,
are delivered as planned, such as the Alameda Corridor freight rail
program in Southern California and Singapore’s North East rail
line. Based on my experience and research, here are five ways to
improve the odds of success.
Manage
more than just time and budget. For
infrastructure projects, the emphasis is usually on completing the
project on time and on budget. These matters are important, but they
are not everything. A project that is completed punctually but that
doesn’t work well cannot be considered a success. Think of a new
airport or highway that handles less than the planned capacity
because of design changes or cut-backs during construction but was
completed on time and on budget. These functional elements need to be
tracked just as rigorously as the traditional parameters of cost and
schedule.
All
these factors must be defined, tested, proven, and managed from early
planning through commissioning. To do so, the project owner should
appoint someone to monitor how well the project meets all
requirements. The designer, construction manager, or contractor are
usually unable to provide a dispassionate overview. The monitor
should have the authority to prevent changes to the configuration of
the project during design and construction that could have an impact
on the planned operational performance. When a European airport did
this, the outside hire helped to significantly reduce capital
spending by examining the plans for risk and by working with the
airport authorities to increase flexibility for future expansion.
Apply
the appropriate delivery method for each project. Particularly
in the public sector, there is a tendency to opt for the same
delivery method—such as design-bid-build, construction manager at
risk, or design-build—for all capital projects. This is
understandable. Doing the usual is safer than trying something new.
But
conditions can differ. It makes much more sense to evaluate each
project and then decide which method is most appropriate. This means
evaluating a wide array of factors, such as permitting and regulatory
status, land-site control, owner priorities, geotechnical and
subsurface analysis, organizational and supply-chain capacity, degree
of risk, and potential for changes. This evaluation can clarify which
delivery method fits the risk profile. One North American
infrastructure agency uses a “value for money” assessment when it
is considering using a nonstandard delivery model. It compares total
project costs for each option, thereby verifying that the chosen
delivery model was best suited for that particular project. This may
sound like an obvious approach; in my experience, though, few
agencies do it.
Balance
risks. Organizations
that work with designers and contractors must accept that this is a
business relationship fraught with risks—and be willing to share
them. Counterintuitively, this may actually lower the risks for
everyone and make the project run more smoothly.
Profit
margins for infrastructure companies are typically low. Taking a hit
on a single big project can jeopardize their financial well-being.
Therefore, if the owner tries to shift all or most risks and
liabilities over to these companies, the latter will naturally seek
ways to cover or hedge them through higher bid costs, additional
contingencies, costly insurance policies, or adversarial contract
management. This approach may lead to disputes, delays, and failure.
During
the construction of Heathrow’s Terminal 5, the parties managed risk
more collaboratively. (Terminal 5 opened in March 2008 on schedule
and within budget; for more, see “Remember the people: The
foundation for success in 21st-century infrastructure,” inVoices
on Infrastructure,
Spring 2016.) The client, Heathrow Airport, held a comprehensive
insurance policy to cover all risk. Instead of a traditional
client-contractor relationship, Heathrow treated the different
partners like team members. It invited them to work together to solve
complex issues during delivery and to help Heathrow find the
technical solutions that worked best for the project as a whole. This
allowed all the parties to focus on finding ways to keep the project
on schedule and within budget. That, in turn, helped the different
companies meet their own obligations. This is similar to the
successful alliance-contracting approach that has been used
extensively in Australia on large projects, in which the project
owner, designer, and contractor work under one contractual agreement
to jointly deliver the project.
Involve
operations and maintenance experts from the start. Projects
that have progressed smoothly through the design and construction
phases still have a chance of hitting a rough patch. This can happen
when the people who will ultimately operate and maintain the asset,
whether it is a rail system, port, terminal, or highway, are shut out
of the decision-making process during design and construction.
Decisions
affecting the total cost of ownership—including access and
logistics, spare-parts management, and trade-offs of initial versus
operating costs—are critical. The costs associated with operating
and maintaining infrastructure assets over a 20- to 30-year span run
many times higher than the costs for design and construction.
Therefore, the costs must be considered in the planning and design.
That requires making operations and maintenance experts part of the
team from the beginning. Many oil and gas companies use this approach
for big capital projects. They have found that doing so means that
projects are ready to run on completion and that operations and
maintenance personnel are prepared as well.
McKinsey&Company
Managing big projects: The lessons of experience
Reviewed by Unknown
on
Friday, May 20, 2016
Rating:
No comments: